Evidence and Review
Evidence is the record that field work happened. It may be a file reference, a link, a field note, a row imported from a CSV file, or another record that supports an activity.Evidence Section
Open Operations, then select Evidence. The Evidence section includes:- Field evidence form
- Evidence list
- Evidence review queue
- Field data import
Submitting Field Evidence
A user with submission access can submit evidence when activities exist. The form asks for:| Field | Meaning |
|---|---|
| Activity | The activity this evidence supports |
| Evidence title | A short, recognizable name for the submission |
| Evidence link or file reference | A URL, file reference, or storage reference |
| Field notes | Context about the evidence |
Evidence Statuses
Evidence can move through these statuses:| Status | Meaning |
|---|---|
| Submitted | The evidence has been received and is waiting for review |
| Approved | The evidence has been accepted |
| Needs correction | The reviewer needs the field team to correct or clarify something |
| Rejected | The evidence does not meet the required standard |
Review Queue
The review queue shows evidence that is waiting for a decision. Reviewers can:- Approve
- Request correction
- Reject
When to Approve Evidence
Approve evidence when:- It matches the selected activity.
- It contains enough information to verify the field action.
- The notes are clear.
- The file reference or link is usable.
- The submission does not create a data quality concern.
When to Request Correction
Request correction when:- The evidence is probably valid but incomplete.
- The activity is correct but the notes are unclear.
- The file reference is missing or incorrect.
- More field context is needed.
When to Reject Evidence
Reject evidence when:- It does not match the activity.
- It is too incomplete to verify.
- It duplicates a record that should not be duplicated.
- It creates a serious quality concern.
Field Data Import
The Field data import area lets authorized users paste CSV data for bulk field submission records. Required columns:titleactivity_id
notesevidence_urlfield_datelatitudelongitude
Import Results
After an import, ProjectDesk shows:- Imported count
- Skipped count
- Error count
- Error summary, if applicable